Wood Floor Installation - Sub-Floor Preparation
Before beginning your hardwood floor installation, it's essential that you thoroughly clean the subfloor. Remove all paint, oil, grease, sealers, drywall patch, dirt, adhesives, or any other contaminates.
The sub-floor must be dry
Concrete must be cured for at least 60 days and visually dry with no history of moisture problems. When testing for moisture, it's suggests utilizing the industry-standard calcium chloride test or the Tramex
Moisture Encounter (5% max). Wood, OSB, or plywood sub-floors must be 14% maximum.
The sub-floor must be level (flat)
Check the sub-floor to determine that it is level to within 3/16" in a 10 ft. radius, or 1/8" in a 6 ft radius. (Loose or hollow spots in a hardwood floor are mostly due to uneven variations in the sub-floor.)
Fill low areas with high-compression, latex-based Portland leveling patches, adhering to the manufacturer's guidelines. Sand or grind high areas.
The sub-floor must be structurally sound
There must be no light-weight concrete under 100 lb. Test Cured. The floor joist must be no more than 16" on center, or the floor must be reinforced by adding additional underlayment or using cross-blocking.
Crawl spaces must have the soil covered (6 mil. black poly) and must allow open ventilation of 1.5% for the total floor area.
OSB must be APA-rated and maintained in a controlled environment, before and after installation, and not exposed to excessive moisture.
Underlayment-grade particleboard can only be used as a subfloor if you are performing a glue-down installation of engineered wood flooring.
If the sub-floor is radiant-heated, you must install engineered or longstrip flooring only.
Acclimate pre-finished hardwood floor according to the following:
- Solid - 72 hours
- Engineered - 48 hours
- Longstrip - No acclimation required
- Allow an additional 24-hours acclimation time in very dry or humid areas.
|
Flooring
|
Installation Method
|
Requirements
|
|
Solids
|
Nail/Staple
|
On/Above Grade only
Expansion Space - 3/4", length 1%, crossgrain 15%
Acclimate 72 hours minimum
|
|
Engineered
|
Glue
Staple
Nail
|
All grade levels allowed
Mix cartons
Expansion space - 1/2"
Acclimate 48 hours minimum
|
|
Longstrip
|
Glue
Float
|
All grade levels allowed
Mix Cartons
Expansion space: 1/2"
No acclimation required
|
|
Copyright © 2006 i-hardwoodflooring.com. All rights reserved.
This website and the materials and information you find on this website are provided "as is", without warranty of any kind, either express or implied, including without limitation any warranty for information, services, or products provided through or in connection with the service and any implied warranties of merchantability, fitness for a particular purpose, expectation of privacy or non-infringement.
For safety, use caution, care, and good judgment when following the procedures described in this website. This website can not assume responsibility for any damage to property or injury to persons as a result of misuse of the information provided.
Consult your local building department for information on building permits, codes, and other laws as they apply to your project.



|